2021 ADA Improvements

CIP 20-09 & 21-06

Phase: Construction

Anticipated Construction Start: July 2021

Anticipated Construction Completion: October 2021

Project Description

Construct required Americans with Disabilities Act (ADA) improvements to pedestrian paths at various locations throughout Woodland. 

This year’s project includes curb ramps at Buckeye and Cottonwood, Buckeye and West, West and Central, Cleveland and Woodland, Locust and Grafton, Cottonwood and Lewis, Cleveland and Park, and Southwood and Willow.

Status Updates

ADA curb ramps are complete at all locations. The remaining work includes minor asphalt patching and striping at various locations.

We currently expect all work to be complete by mid to late October 2021. 


Buckeye & West

ADA 2021 Buckeye and West


Willow & Southwood

ADA 2021 Willow and Southwood