2021 Road Maintenance Project 

CIP 20-02

Phase: Construction

Anticipated Construction Start: July 2021

Anticipated Construction Completion: Winter 2021

Project Description

This project includes microsurfacing W. Cross (CR98 to West), W. Lincoln (CR98 to West), Cottonwood (W. Main to Gibson), Cottonwood (El Dorado to Gibson), and Clover (West to Walnut). The project also includes a grind and overlay of West Street from the southern City limits to Gibson Road.

Status Updates

The project is currently underway and microsurfacing work will be completed the week of September 13. Work on West Street will begin September 20 and is anticipated to finish that week. Restriping of the roadways will be completed approximately two weeks after surfacing to allow cure time for the road materials.

Road Surface Seal Example