Sports Park Drive Pedestrian Overcrossing Project

CIP 17-22

Phase: Construction

Construction Start: October 2021

Anticipated Construction Completion: Fall 2022

Project Description

The complete project consists of the design and construction of a bicycle/pedestrian crossing over SR-113 along the alignment of Sports Park Drive to Farmers Central Road.

This project, along with planned Spring Lake development, will complete a bicycle/pedestrian connection along the south side of town from CR 102 to East Street. This pathway is planned for extension from East Street to Ashley Avenue. This will enable residents to access the existing north/south bike lane corridors throughout the City. This project will provide bicycle/pedestrian access to the Community Center/Sports Park and to the growth areas on the east side of SR-113.

Status Updates

Construction is currently underway. During Summer 2022, the City’s contractor installed the main bridge concrete components, with the bridge deck placed on the first week of August. Work continues on the remaining bridge items; removal of the falsework (temporary support structure) is estimated for late October. Electrical work for lighting the path has started along with the irrigation system for the landscape along the path, on both sides of 113. 

Construction progress as of July 2022 

Bike Ped Overcrossing 07.20.22

Pouring the bridge deck concrete in August 2022 

sunrise concrete at sports park drive bike ped overcrossing