East Main Street Improvement Project

CIP 13-05

Phase: Construction

Anticipated Construction Completion: Spring 2023

Project Description

This project is located on East Main Street from East Street to Pioneer Avenue and will install a landscape-separated, off-street bike path on the north side of E. Main between Pioneer Avenue and Matmor Road. 

The project also includes microsurfacing the pavement and restriping the road between East Street and Pioneer Avenue. Restriping will narrow travel lanes to reduce vehicle speeds and widen existing on-street bike lanes as well as add bike lanes where they do not currently exist. Additionally, the project will install curb and gutter, landscape, fencing, irrigation, and storm drainage improvements.

Status Updates

As of the beginning of 2023, construction is near completion. The City's contractor has finished the multi-use path, fencing, and landscaping on the north side of East Main between Pioneer and Matmor. Striping is 90% complete and will be fully completed as weather allows.

Overhead View of Project Area: East to Pioneer

E Main Project Overhead